How to: Open Microsoft Project Plan in EasyTaskLink Database
There are two ways to open a Microsoft Project Plan that had been published into EasyTaskLink database. You can use the Project Center screen or use Microsoft Project.
1. Open Microsoft Project.
2. From EasyTaskLink toolbar clicking the EasyTaskLink button and select Open an Open a Project screen is display with the list of Microsoft Project Plan that was previously published into EasyTaskLink database.
3. Highlight the project then click the Open button will open the MPP file.

1. Double Click the MPP file from the Project Center will open the Microsoft Project Plan.